Jurisdiction What council did When
Oakville Interim Control By-law 2026-129: one-year pause on data centres; no applications were on file. Planning study ordered (noise, vibration, emissions, compatibility, energy supply, water, utilities). Aug 11, 2026
Mississauga Interim control by-law: one-year pause on facilities of 10 MW and over, extendable to two; one application on file (Tenth Line West). Interim staff report to council in fall 2026 on study scope and consultation. Sept 16, 2026
Sault Ste. Marie Approvals of large data centres frozen until a municipal framework is in place, expected early 2027; a 400 MW proposal in early planning. Sept 2026
Hamilton Committee of Adjustment refused a conforming 76-hectare severance for the Steelport data-centre campus after staff recommended approval; 1,600-plus letters. Council advanced a pause June 24, then defeated it July 15. Applicant’s appeal before the Ontario Land Tribunal (OLT-26-000693). June 4, 2026
Toronto Staff directed to develop a Toronto approach to AI data centres (item MM39.47). On July 30, 2026 council adopted MM43.75, 25–0: all AI data-centre approvals aligned to that review, the local councillor notified of every application, a staff report to Planning and Housing in the first half of 2027, and a noise peer review ordered on the 3650 Danforth Avenue site-plan file. July 30, 2026
Ottawa Staff directed to develop an assessment framework and possible policy amendments; council to be told of large-scale proposals so it can consider case-by-case moratoria. Aug 2026
Milton A proposed one-year pause was defeated; council directed staff to study data centres instead. Sept 14, 2026
Burlington A temporary moratorium was defeated; staff directed to review the town’s data-centre rules. July 2026
Waterloo Region Staff directed to report to council in early 2027 on the implications of data-centre development. Aug 2026
Province and federal
Province of Ontario Draft Data Centre Playbook released for comment: a system-impact assessment and a strategic-priority assessment, with ‘invest in communities and earn public confidence’ among the pillars. Comment period closed September 12, 2026. The final version is to accompany the province’s AI Industrial Strategy, which the backgrounder says is due this fall; no separate date is given. Aug 13, 2026
Government of Canada Responsible Data Centre Development Principles launched with 23 signatories; 19 more added September 22, 2026, for 42. The release contains no numeric target, monitoring or enforcement mechanism. Sept 3, 2026

Sources

Sault Ste. Marie
Toronto

Province and federal

Province of Ontario

Changelog

  • 2026-10-30 — Site published.
  • 2026-10-30 — Initial publication: nine municipalities, Province of Ontario, Government of Canada. Sources as listed under the table.